Solar and Battery Backup on Sanibel and Captiva

When Ian washed out sections of the Sanibel Causeway in 2022, the islands were reachable only by boat and helicopter until temporary repairs reopened the road about three weeks later. Islanders remember that. On Sanibel and Captiva, backup power is about running a home through a long restoration, not riding out a flicker.
We have installed and serviced solar on the islands, and this page is what we have learned from that work.
Sanibel and Captiva at a glance
- Electric utility: LCEC
- Permits issued by: the City of Sanibel on Sanibel; Lee County on Captiva
- Flood risk: Surge reached across most of both islands in Helene and Ian
- Wind exposure: Very high on the Gulf side, with salt on everything

What is different about an island with one road
When the causeway goes, everything waits
Crews could not drive onto Sanibel for weeks after Ian, and that includes line crews, electricians and anyone with a replacement part. Backup here has to carry the house through a long wait, so we size batteries for days and tell you plainly what a whole-home design costs versus protecting only the loads that matter.
Two jurisdictions on a short stretch of road
Sanibel runs its own building department and has its own expectations. Captiva is unincorporated, so it goes through Lee County. We plan the schedule and the paperwork around whichever applies to your address.
The disconnect LCEC wants, and what it means for you
LCEC requires a manual disconnect on net-metered systems 10 kW and under. We include it in our designs and plan its location with your architect so it is accessible without being an eyesore.
Big homes, quiet equipment
Captiva and Gulf-front Sanibel homes tend to be large and architect-designed. The equipment wall, conduit routes and roof layout get planned with your builder so the result is clean, serviceable and out of sight.
Helene, Milton and a long memory of Ian
Helene passed about 150 miles west of the islands on Sept. 26, 2024, and still pushed roughly 5 feet of surge onto Sanibel, according to city officials. Sanibel’s weirs were opened days ahead, but the surge overtopped them and held salt water on the island for more than 19 hours. On Captiva, flooding and sand covered Captiva Drive. SCCF’s chief executive called it a surge event, not a rainfall event, which is the point for equipment: water came from below, not above.
That is why we put every battery, inverter and gateway above flood elevation, and why a ground-level utility room is a plan we try to talk owners out of.
Where we work on the islands
- West Gulf Drive and the Gulf-front streets: salt and wind exposure first
- The Dunes: golf community with mature landscaping and shade to work around
- East End and the Lighthouse area: older homes with high surge exposure
- Captiva Village and South Seas: unincorporated, Lee County permits
When a seller left you with a system you cannot use
LCEC has warned members about solar sellers who falsely claim to partner with the cooperative. Its spokesperson put it plainly: LCEC does not partner with any solar company. After a storm, more pitches arrive, and some of them are built on the idea that the electric company is about to raise your rates. Florida homeowners in other parts of the state have ended up with obligations lasting up to 25 years. If that is you, read our guides on what to do when a solar contractor disappears and solar lease scams targeting seniors.
Our work on Sanibel and Captiva
Our job records show installs, repairs and service on Sanibel going back to 2019 and on Captiva in 2026.
We are working with the Sanibel Community House on a commercial solar and battery design, and we advised SCCF on solar-ready electrical design for its campus, including how rapid shutdown works building by building. We have also taken over systems on the islands that other installers abandoned or left unfinished.
On Captiva, in 2026 we completed a ten-panel array and a battery addition at the same home. Across Lee County we have completed thousands of jobs, and that count includes service and repairs.
How we design for the islands
- Whole-home or critical-load backup sized for multi-day outages
- All equipment above flood elevation
- Coordination with builders and architects before the roof is framed
- Hardware and enclosures chosen for salt exposure
- The LCEC manual disconnect included on systems 10 kW and under
Island questions we hear
Can batteries really carry a whole island home?
Many can, if they are sized for it and the big loads are managed. Pool pumps and second AC systems are where the cost climbs. We show you whole-home against the loads that truly matter.
Do you work with my builder?
We prefer it. Equipment rooms, conduit paths and roof layouts are easier on paper than on a finished house. If the house is already built, we walk it with you first and plan around what is there, so nothing gets forced into a spot that will cause trouble later.
Do you install on Captiva?
Yes. Captiva is unincorporated, so permits come from Lee County rather than the City of Sanibel.
Does LCEC require anything special for my system?
For net-metered systems 10 kW and under, LCEC requires a manual disconnect. We include it.
Start with a design conversation
Tell us your address, your builder if you have one, and what you want to keep running when the causeway is closed.